Nexans – TenneT frame agreement
Worked with engineering management and systems engineering in support of Nexans two first projects of the TenneT frame agreement BalWin3 and LanWin4. The complete scope included 2160 km of 525 kV PEX HVDC cable to be installed before 2030.
-
420 kV Åfjord-Snilldal, Surna-Viklandet
We provided engineering management to Statnett for the development of about 200 km powerlines, four 420 kV transformer station extensions and subsea cable crossing of Trondheimsfjorden for a period from 2021-2023.
-
Fortescue Green Hydrogen
We are proud to provide management of grid connection aspects in support of Fortescue in their mission to create green hydrogen plants in Norway. Since 2019 we have been part of a team screening sites and developing the projects, resulting in two sites being developed in parallell at Holmaneset and Hemnes.